Project

Marston Road

40 residential properties on a sloping site

The Marston Road development in Lidlington, Bedford comprises the construction of 40 residential properties on a sloping site.

A particular challenge came from the presence of a slope to the south east of the site with mapped landslide deposits and proposals to cut into the toe of the slope that had the potential to become instable.

Walsh provided geotechnical consultancy to assess the slope stability at the site, including review of ground investigation data, initial appraisals and site visits, analysis of existing and proposed cases and an options appraisal for remedial work.

A solution loading the slope of the toe and introducing a counterfort drain system was reached. The earthworks and drainage specifications were then developed with Walsh geotechnical and civils teams working in collaboration.

Client 
  • Jarvis Contracting
Completion DateTBC
Sectors 
Specialisms 
Location 
  • Bedford
  • Lidlington

Explore Related Projects

Mixed Use

Harold Hill Family Welcome Centre

Structural scheme designed for future-proof adaptation [...]

Read more

Mixed Use

Cantium Retail Park

Planning support to prove feasibility of inner-city retail park regeneration [...]

Read more

Mixed Use

Southernwood Retail Park

Supporting a successful first-time planning application [...]

Read more

Infrastructure

Ladbroke Grove (Project Flourish)

Supporting hybrid planning application for major regeneration scheme [...]

Read more

Residential

Malt Street Regeneration

Innovative foundation and piling design to gain third-party approvals on complex, multiphase regeneration project [...]

Read more

Mixed Use

Crossharbour District Centre

Planning support for a resi-over-supermarket mixed-use redevelopment & regeneration [...]

Read more

Taking Sustainability Seriously

Sustainability is in our DNA and we have our own ambitious goals to achieve Net Zero as a business and with our designs. With innovative in-house monitoring tools, Walsh clients have seen on average reductions of 10-20% total embodied carbon, with some of our flagship work achieving 60-70% reductions compared with baseline figures.